Question: Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 21 days respectively, compute the expected activity time range (time +/-
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 21 days respectively, compute the expected activity time range (time +/- standard deviation) for this activity.Single choice.
(1 Point)
8 +/- 1
8 +/- 2
8 +/- 3
4 +/- 4
None of the answers.