Question: QUESTION 3 10 P Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 15 days respectively, compute the PERT expected

QUESTION 3 10 P Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 15 days respectively, compute the PERT expected activity time for this activity. 10 08 Onone of these 7