Question: Given an EAC of $ 1 0 , 0 0 0 and a BAC of $ 1 5 , 0 0 0 , the project
Given an EAC of $ and a BAC of $ the project is expected to be completed
Group of answer choices
over budget
under budget
over budget but ahead of schedule
under budget but behind schedule
on budget