Question: Given an expected project completion time of 26 weeks and a project variance of 8 weeks, what is the approximate probability of completing the project

Given an expected project completion time of 26 weeks and a project variance of 8 weeks, what is the approximate probability of completing the project within 24 weeks? Pick the closest answer from provided options.

using a normal distribution chart

Z=(Tc - Te)/Project std deviation, where Tc = desired project completion time; Te = expected project completion time;

Std deviation = Sq root of Variance