Question: Given an expected project completion time of 26 weeks and a project variance of 9 weeks, what is the approximate probability of completing the project

Given an expected project completion time of 26
Given an expected project completion time of 26 weeks and a project variance of 9 weeks, what is the approximate probability of completing the project within 20 weeks (Tc)? Pick the closest answer from provided options. Normal distribution table is available on BB/Course Documents or can be computed using Excel Z=(TC. Tey/Project std deviation, where Tc = desired project completion time; Te = expected project completion time; Std deviation - Sq root of Variance 0.0255 0.2200 0.7611 0.0228