Question: Given: Any network where the critical path is determined by four activities P Q, R, and S; and the early finish for the network is

Given: Any network where the critical path is

Given: Any network where the critical path is determined by four activities P Q, R, and S; and the early finish for the network is calculated as 12days. Reg'd: a) If the standard deviation value for each of the four critical activitiesis (2/3), calculate the probability of completing the project isin 14 days; and ii) in 10 days. Value (2) 1.0 1.5 2.0 2.5 Area 0.3413 0.4332 0.4772 0.4938 b) How long would it take to complete this project with 100% certainty

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!