Question: Given are the following details pertaining to a preloading project: Surcharge: Dp = 8 0 kPa Consolidating soil: w = 5 0 % ; wl

Given are the following details pertaining to a preloading project:
Surcharge: Dp =80 kPa
Consolidating soil:
w =50%; wl =71%(liquid limit); Ip =47%(plasticity index)
=1.7 t/m3; Cc =0.7; Cv =0.6 m2/year; Ch =1.2 m2/year
L =20 m (longest drainage path); d =0.10 m; S =2 m (triangular spacing)
a) Determine the average consolidation ratio Uvr (combined vertical and radial drainage)
after 10 months of preloading.
b) Calculate the settlement obtained after 10 months with and without drains