Question: Given seven tasks, A, B, C, D, E, F, and G, construct the precedence graph from the following precedence relations: Then, assuming that all tasks

 Given seven tasks, A, B, C, D, E, F, and G,

Given seven tasks, A, B, C, D, E, F, and G, construct the precedence graph from the following precedence relations: Then, assuming that all tasks arrive at time t = O. have deadline D = 20, and computation times 2 3, 3, 5, 1, 2, 5, respectively, modify their arrival times and deadlines to schedule them by EDF Show ALL the work! Including only the solution schedule will not be sufficient