Question: Consider seven tasks, A , B , C , D , E , F , and G , with precedence relations among them as: A

Consider seven tasks, A, B, C, D, E, F, and G, with precedence relations among them as: AC,BC,BD,CE,CF,DF,DG where xy implies y can start its execution only after the completion of x's execution. The task graph representing this precedence relation is given below.
Assume that all tasks have arrived at t=0, have deadlines d=25, and their computation times are 2,3,3,5,1,2,5 respectively. Modify the deadlines of the tasks similar to EDF*. Consider that the new release time of a task can be replaced by the maximum between the finishing time of its immediate predecessors and the release time of that task. With the modified release times and deadlines, construct the EDF schedule. Assume that period of each task is same as its deadline.
a.B,A,D,C,E,F,G
b.A,B,D,C,E,F,G
c.B,A,C,D,E,F,G
d.A,B,C,D,E,F,G
a.
b.
C.
d.
 Consider seven tasks, A, B, C, D, E, F, and G,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!