Question: Given small project data below. Match each question with its answer. Act Pred NT(days) CT(days)NC($) A 6 3 870 B A 5 3 560 C

Given small project data below. Match each

Given small project data below. Match each question with its answer. Act Pred NT(days) CT(days)NC($) A 6 3 870 B A 5 3 560 C 4 3 590 D 4 3 360 E B, C, D 2 1 965 CC($) 450 340 550 350 800 What is the sequence of crashing? Choose...