Question: Given that the AC = 5 0 0 , PV = 4 0 0 and EV = 3 0 0 , this project is currently
Given that the AC PV and EV this project is currently budget and schedule.
Multiple Choice
under, ahead of
over, ahead of
over, behind
on on
under, behind