Question: Given that the AC = 5 0 0 , PV = 4 0 0 and EV = 3 0 0 , this project is currently

Given that the AC =500, PV =400 and EV =300, this project is currently _________ budget and ______ schedule.
Multiple Choice
under, ahead of
over, ahead of
over, behind
on, on
under, behind