Given the activities described by the following table:
| Activity | Expected Time | STD of Time Estimate | Predecessor |
| A | 7 | 2 | - |
| B | 3 | 1 | A |
| C | 9 | 3 | A |
| D | 4 | 1 | B,C |
| E | 5 | 1 | B,C |
| F | 8 | 2 | E |
| G | 8 | 1 | D,F |
| H | 6 | 2 | G |
a. What is the critical path and project time?
A, C, D, G, H - 45
b. What is the project variance and STD? 23 and 4.8
23 and 4.8
c. Find the probability that the project will take more than 49 periods to complete
10.6%