Question: Given the activities described by the following table: Activity STD of Time Estimate Expected Time 7 Predecessor A 2 B 3 1 A C 9

Given the activities described by the following
Given the activities described by the following table: Activity STD of Time Estimate Expected Time 7 Predecessor A 2 B 3 1 A C 9 3 A D 4 1 B,C B,C E 5 1 F 8 2 E G 8 1 D.F H 6 2 G a. What is the critical path and project time? A, C, E, F, G, H-43 b. What is the project variance and STD? 23 and 4,8 b. Find the probability that the project will take more than 49 periods to complete 89.4% %