Question: Given the activities, time estimates and dependency relationships: Duration ( days ) Activity Predecessor Optimistic Most Likely Pessimistic A * * * 3 5 1
Given the activities, time estimates and dependency relationships:
Duration days
Activity
Predecessor
Optimistic
Most Likely
Pessimistic
A
B
C
A
D
B
What is the estimated standard deviation for the critical path?
Group of answer choices
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
