Question: Given the activities, time estimates and dependency relationships: Duration ( days ) Activity Predecessor Optimistic Most Likely Pessimistic A * * * 3 5 1

Given the activities, time estimates and dependency relationships:
Duration (days)
Activity
Predecessor
Optimistic
Most Likely
Pessimistic
A
***
3
5
13
B
***
4
7
10
C
A
5
7
15
D
B
8
9
22
What is the estimated standard deviation for the critical path?
Group of answer choices
2.78
2.54
2.36
1