Question: Given the activities whose sequence is described by the following table i) Draw the appropriate activity-on-arrow (AOA) network diagram neatly. Calculate ES, EF, LS,
Given the activities whose sequence is described by the following table i) Draw the appropriate activity-on-arrow (AOA) network diagram neatly. Calculate ES, EF, LS, LF and slack for each activity. ii) iii) Identify the critical activities and calculate the project completion time. iv) Determine the probability (In Percentage) that the project will be complete by the 37th day. Activity A B C D E F G H I K Immediate Predecessor(s) - A B C B C D. E G F, H I F Time t Variance (days) 7 5 5 3 6 11 4 3 5 7 10 1 0.25 0.15 0.75 0.5 0.1 0.25 0.2 1 0.2 0.4
Step by Step Solution
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Answer Lets start by drawing the ActivityonArrow AOA network diagram A7 B5 E6 J7 K10 C5 F11 I5 D3 G4 ... View full answer