Question: Considering the following information for a project: Activity Crash Time (weeks) A B C D E F G H I Immediate Predecessor - A
Considering the following information for a project: Activity Crash Time (weeks) A B C D E F G H I Immediate Predecessor - A B C F G D. E Normal Time (weeks) 4 5 6 8 5 8 4 5 3 2 4 5 4 2 7 3 4 3 Crash Cost/week (S) 200 40 100 70 90 300 140 120 i) What is the project completion date? ii) Give a detailed plan of reducing the project completion time by 31 weeks. iii) What is the minimum possible time of completing the project.
Step by Step Solution
3.38 Rating (154 Votes )
There are 3 Steps involved in it
i Project Completion Date To determine the project completion date we need to calculate the critical ... View full answer
Get step-by-step solutions from verified subject matter experts
