Question: Given the activity list below, create the network schedule, determine the critical path and calculate the float of activity E ( 1 2 marks )

Given the activity list below, create the network schedule, determine the critical path and calculate the float of activity E (12 marks)
\table[[Activity,Successors,Duration (days)],[A,F,6],[B,,5],[C,,8],[D,E and F,4],[E,G,8],[F,B and G,7],[G,H,5],[H,C,7]]