Question: Given the activity table ( Table of Dependencies ) below for a certain project: table [ [ Activity , Predecessor,Duration ( Weeks ) ]

Given the activity table (Table of Dependencies) below for a certain project:
\table[[Activity,Predecessor,Duration (Weeks)],[A,-,1],[B,A,1],[C,A,2],[D,A,3],[E,B,2],[F,C,2],[G,E,3],[H,D,F,G,2]]
a) Calculate the project duration (using the forward pass), calculate the critical path (using the backward pass)(10 Marks)
b) Based on the answers obtained in question a) and the Table of Dependencies; construct a Gantt chart. (10 Marks)