Question: Given the activity table (Table of Dependencies) below for a certain project: Activity Predecessor Duration (Weeks) A - 1 B A 1 C A 2

Given the activity table (Table of Dependencies) below for a certain project:

Activity

Predecessor

Duration (Weeks)

A

-

1

B

A

1

C

A

2

D

A

3

E

B

2

F

C

2

G

E

3

H

D,F,G

2

4.1. Draw a network diagrams without durations as well as the one with durations. (5 Marks)

4.2. Calculate the project duration (using the forward pass), calculate the critical path (using the backward pass) and calculate the total float (slack) for the project activities. (5 Marks) 4.3. Based on the answers obtained in question 4.1. & 4.2.; draw a Gantt chart. (5 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!