Question: Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI. Consider

Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI.

Consider it is currently at the end of Month 2. This implies that task 6 was planned to be completed but was not started. Be sure to show all of your work.

Planned Schedule and Budget
Actual Cost
Task
Month 1
Month 2
Month 3

1
$4,000


$6,000
2
$1,000


$4,000
3
$3,000


$4,000
4

$5,000

$1,000
5

$5,000

$4,000
6

$3,000


7


$1,000

8


$2,000

9


$4,000

Total
$8,000
$13,000
$7,000
$19,000

Step by Step Solution

3.50 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this problem we will go through the project management calculations step by step These include Schedule Variance SV Cost Performance Index CP... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!