Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC
Fantastic news! We've Found the answer you've been seeking!
Question:
Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI.
Consider it is currently at the end of Month 2. This implies that task 6 was planned to be completed but was not started. Be sure to show all of your work.
Planned Schedule and Budget | Actual Cost | |||
Task | Month 1 | Month 2 | Month 3 | |
1 | $4,000 | $6,000 | ||
2 | $1,000 | $4,000 | ||
3 | $3,000 | $4,000 | ||
4 | $5,000 | $1,000 | ||
5 | $5,000 | $4,000 | ||
6 | $3,000 | |||
7 | $1,000 | |||
8 | $2,000 | |||
9 | $4,000 | |||
Total | $8,000 | $13,000 | $7,000 | $19,000 |
Related Book For
College Accounting A Practical Approach
ISBN: 978-0132564441
11th Canadian Edition
Authors: Jeffrey Slater, Brian Zwicker
Posted Date: