Question: Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI. Consider
Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI.
Consider it is currently at the end of Month 2. This implies that task 6 was planned to be completed but was not started. Be sure to show all of your work.
| Planned Schedule and Budget | Actual Cost | |||
| Task | Month 1 | Month 2 | Month 3 | |
| 1 | $4,000 | $6,000 | ||
| 2 | $1,000 | $4,000 | ||
| 3 | $3,000 | $4,000 | ||
| 4 | $5,000 | $1,000 | ||
| 5 | $5,000 | $4,000 | ||
| 6 | $3,000 | |||
| 7 | $1,000 | |||
| 8 | $2,000 | |||
| 9 | $4,000 | |||
| Total | $8,000 | $13,000 | $7,000 | $19,000 |
Step by Step Solution
3.50 Rating (160 Votes )
There are 3 Steps involved in it
To solve this problem we will go through the project management calculations step by step These include Schedule Variance SV Cost Performance Index CP... View full answer
Get step-by-step solutions from verified subject matter experts