Question: Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI. Consider
Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI.
Consider it is currently at the end of Month 2. This implies that task 6 was planned to be completed but was not started. Be sure to show all of your work.
| Planned Schedule and Budget | Actual Cost | |||
| Task | Month 1 | Month 2 | Month 3 |
|
| 1 | $4,000 |
|
| $6,000 |
| 2 | $1,000 |
|
| $4,000 |
| 3 | $3,000 |
|
| $4,000 |
| 4 |
| $5,000 |
| $1,000 |
| 5 |
| $5,000 |
| $4,000 |
| 6 |
| $3,000 |
|
|
| 7 |
|
| $1,000 |
|
| 8 |
|
| $2,000 |
|
| 9 |
|
| $4,000 |
|
| Total | $8,000 | $13,000 | $7,000 | $19,000 |