Question: Given the Bill of Material (BOM) tree structure pictured below, which item(s) should the company who assembles the wheelbarrow forecast? Group of answer choices Nothing
Given the Bill of Material (BOM) tree structure pictured below, which item(s) should the company who assembles the wheelbarrow forecast?

Group of answer choices
Nothing should be forecast - this is an example of dependent demand
The components (in blue)
Wheelbarrow
Subcomponents - wheels, legs, handles and bucket
Multilevel bill of materials This BOM represents the multiple components used in building a product. FINISHED PROJECT SUBASSEMBLIES COMPONENTS Axle Wheel Spacer Axle brackets Leg braces Legs Wheelbarrow 2-inch bolts Wheel guard Handles Spacers 3-inch bolts Bucket/tray 5-inch boltsStep by Step Solution