Question: Given the circumstances surrounding the project, the project manager has decided to Fast Track the Project. This will likely result in: Reducing the number of

Given the circumstances surrounding the project, the project manager has decided to Fast Track the Project. This will likely result in:
Reducing the number of people involved on the project
Decreased project costs
A lesser amount of supervision required by senior management
A smaller duration on the project
 Given the circumstances surrounding the project, the project manager has decided