Question: Given the critical path below, calculate the following: Activity Normal Time Normal Cost Crash Duration Crash Cost A 8 days 150 000 days $12,000 B

Given the critical path below, calculate the
Given the critical path below, calculate the following: Activity Normal Time Normal Cost Crash Duration Crash Cost A 8 days 150 000 days $12,000 B 5 days $2,000 3 days $10.000 C 10 days $9,000 9 days $12,000 The maximum total crash time savings is 3 days and the total cost is 9000 $ The maximum total crash time savings is 3 days and the total cost is 12000 $ The maximum total crash time savings is 4 days and the total cost is 11000 $ c The maximum total crash time savings is 4 days and the total cost is 15000 $ None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!