Question: Given the data and information that follow compute the total direct cost for each project duration. If the indirect costs for each project duration or

Given the data and information that follow compute the total direct cost for each project duration. If the indirect costs for each project duration or $90 (15 time units) $70 (14) $50 (13) $40 (12) and $30 (11) compute the total project cost the for each duration what is the optimum cost time schedule for the project? what is this cost?
Data on page reads as follows in case it's difficult to read from top left to right repeat A-30-1-5-50 B-60-2-3-60 C-0-0-4-70 D-10-1-2-50 E-60-3-5-100 F-100-1-2-90 G-30-1-5-50 H-40-0-2-60 I-200-1-3-200
TOTAL OF NORMAL COST ROW $730 ALSO COST SLOPE FORMULA = CRASH COST -NORMAL COST/ NORMAL TIME - CRASH TIME. SO FOR EXAMPLE CRASH COST = 100 NORMAL COST = 60 NORMAL TIME = 4 CRASH TIME = 2 THAT WOULD BE 100-60 =40 AND 4-2 =2 FOR A FINAL ANSWER OF 40/2=20......I APOLOGIZE IF THAT SEEMED UNECESSARY IM YOU GUYS ALREADY KNOW THAT. PLEASE HELP ME I AM AT MY WITS END WITH THIS AND OVERTHINKING EVERYTHING .
4. Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost? Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost B D E F 30 60 0 10 60 100 30 40 200 1 2 0 1 3 1 1 0 1 WNUN 01 NW 07 50 60 70 50 100 90 50 60 200 $730 H NTI Initial project duration 15 4 A G 5 D 3 5 2 H Total direct cost $730 E B. 2 5 3Step by Step Solution
There are 3 Steps involved in it