Question: Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are
Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15-time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration.
| Activity ID | Crash Cost (Slope) | Maximum Crash Time | Normal Time | Normal Cost |
| A | 30 | 1 | 5 | 50 |
| B | 60 | 2 | 3 | 60 |
| C | 0 | 0 | 4 | 70 |
| D | 10 | 1 | 2 | 50 |
| E | 60 | 3 | 5 | 100 |
| F | 100 | 1 | 2 | 90 |
| G | 30 | 1 | 5 | 50 |
| H | 40 | 0 | 2 | 60 |
| I | 200 | 1 | 3 | 200 |
| Total Direct Cost | $730 | |||

| Project Duration | 15 | 14 | 13 | 12 | 11 |
| Total Direct Cost | $730 | ||||
| Total Indirect Costs | 90 | ||||
| Total Costs | $820 |