Question: Given the data and information that follows in this example, compute the slope and maximum reduction time for each activity. Also compute the total direct
Given the data and information that follows in this example, compute the slope and maximum reduction time for each activity. Also compute the total direct costs for durations 32, 31, 30, 29, 28, and 27 time-units.

Assume indirect costs of $170,$150, $129, $122, $118, and $110, respectively, for each listed duration. What are the optimum project duration and cost?




The answer has to be in the form of the attached tables. Explain in detail the steps.
An example of a crash impact table Direct costs Activity ID Maximum crash time Normal Crash Slope Time Cost Time Cost A 7 50 5 70 B 16 14 15 20 12 4 10 12 D 8 21 7 30 E 6 10 3 19 F 13 22 12 30 The first decision B D TIME 32 LEGEND 16 8 ACT E DUR A 7 6 TOTAL DIRECT COST $ F 12 13 B D TIME A E TOTAL DIRECT COST $ F ACTIVITIES CHANGED --- The 2nd and 3rd decision Exercise 6-2 TIME B D TOTAL DIRECT COST $ A E ACTIVITIES CHANGED F TIME B D A E TOTAL DIRECT COST $ ACTIVITIES CHANGED F The 4th and 5th decisions TIME B D TOTAL DIRECT COST $ E ACTIVITIES CHANGED F TIME B D TOTAL DIRECT COST S A E ACTIVITIES CHANGED F The total impact 27 28 29 30 31 32 Project Duration Total Direct Total Indirect $110 $118 $122 $129 $150 $170 Grand Total
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
