Question: Crashing - Deciding what to tackle first Given the data and information that follows in this example, compute the slope and maximum reduction time for


Crashing - Deciding what to tackle first Given the data and information that follows in this example, compute the slope and maximum reduction time for each activity. Also compute the total direct costs for durations 32, 31, 30, 29, 28, and 27 time-units. Assume indirect costs of $170, $150, $129, $122, $118, and $110, respectively, for each listed duration. What are the optimum project duration and cost? An example of a crash impact table Activity Slope Normal Crash Cost Time Cost The first decision ME 32 B 16 8 A 12 TOTAL DIRECT ACTIVITIES CHANGED The 2nd and 3rd decision B Exercise 6:2 TOTAL DIRECT A C ACTIVITIES CHANGED TOTAL DIRECT F The 4th and 5th decisions TOTAL DIRECT F ACTIVITIES CHANGED C COST $ _ _ C ACTIVITIES CHANGED The total impact 29 $122 $150 $170 Grand Total
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts