Question: Given the data below, using the SPT sequencing rule, which of the following statements is true? Job Processing time ( in days ) Due date

Given the data below, using the SPT sequencing rule, which of the following statements is true?
Job Processing time (in days) Due date (in days)
A 510
B 213
C 78
D 416
A. The average lateness is 2.5.
B. Job B and D are finished after the due date.
C. The makespan is 16.
D. The job sequence using SPT is CADB.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!