Question: Given the data below, using the SPT sequencing rule, determine the completion date and tardiness for each job as well as the average completion time

Given the data below, using the SPT sequencing rule, determine the completion date and tardiness for each job as well as the average completion time and average tardiness for all four jobs. Which of the following statements is true?
Job A: processing time (days)=10, due date (in days)=10
Job B: processing time (days)=5, due date (in days)=8
Job C: processing time (days)=15, due date (in days)=25
Job D: processing time (days)=8, due date (in days)=15
A. The average tardiness is 19.75
B. The average completion time is 6.5
C. Jobs B and D will have no tardiness
D. The tardiness for Job A is 12 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!