Question: Given the data in the following table, calculate cost and duration for Jenny in days. Assume that it is 8 hours working day and Effort

  1. Given the data in the following table, calculate cost and duration for Jenny in days. Assume that it is 8 hours working day and Effort columns below are effort in hours.

    a.

    Cost=$5,000; Duration=2 days

    b.

    Cost=$5,000; Duration=6 days

    c.

    Cost=$4,000; Duration=5 days

    d.

    Cost=$4,000; Duration=3 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock