Question: Given the estimated activity times below and the network in Problem 8 above, what is the critical path probability that the project will be completed

Given the estimated activity times below and the network in Problem 8 above,


Given the estimated activity times below and the network in


what is the critical path probability that the project will be completed within:
(a) 21 days?
(b) 22 days?
(c) 25days?

Activitya 6 1m 7.5 14.5 8.5 10.5 12.5 45 6.5 7.5 8.5 5.5 5.5 9.5 2.5 3.5 Activity a 5.5 7.59.5 4.5 6.5 8.5 2.5 3.5 3.5

Step by Step Solution

3.47 Rating (177 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Task a m b Expected Variance Std Dev A 65 75 145 85 178 133 B 85 105 125 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

84-B-M-L-P-M (448).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!