Question: Given the estimated activity times below and the network in Problem 8 above, what is the critical path probability that the project will be completed
Given the estimated activity times below and the network in Problem 8 above,
.png)
what is the critical path probability that the project will be completed within:
(a) 21 days?
(b) 22 days?
(c) 25days?
Activitya 6 1m 7.5 14.5 8.5 10.5 12.5 45 6.5 7.5 8.5 5.5 5.5 9.5 2.5 3.5 Activity a 5.5 7.59.5 4.5 6.5 8.5 2.5 3.5 3.5
Step by Step Solution
3.47 Rating (177 Votes )
There are 3 Steps involved in it
Task a m b Expected Variance Std Dev A 65 75 145 85 178 133 B 85 105 125 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
84-B-M-L-P-M (448).docx
120 KBs Word File