Question: Given the follow data for a one year project, answer the following in a Word document: Assume you have actual and earned value data at
Given the follow data for a one year project, answer the following in a Word document:
Assume you have actual and earned value data at the end of the second month.
Given: Planned Value (PV) = $23,000
Earned Value (EV) = $20,000
Actual Cost (AC) = $25,000
Budget at Completion (BAC) = $120,000
A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
B. How is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
C. Use the CPI to calculate the estimate at completion (EAC) for this project.
D. Use the SPI to estimate how long it will take to finish this project.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
