Question: Given the following activity network: A3 Az Ag A4 Activity A1 takes 2 weeks, A2 takes 8 weeks. A3 takes 7 weeks, A4 takes 9

Given the following activity network: A3 Az Ag A4
Given the following activity network: A3 Az Ag A4 Activity A1 takes 2 weeks, A2 takes 8 weeks. A3 takes 7 weeks, A4 takes 9 weeks, A5 takes 2 weeks. What is the earliest project completion time? weeks (round to the nearest integer)