Question: help ! Given the following activity network: A3 A1 A2 A4 Activity A1 takes 2 weeks, A2 takes 6 weeks, A3 takes 3 weeks, A4

help ! help ! Given the following activity network: A3
Given the following activity network: A3 A1 A2 A4 Activity A1 takes 2 weeks, A2 takes 6 weeks, A3 takes 3 weeks, A4 takes 7 weeks, A5 takes 4 weeks. What is the earliest project completion time? 12 weeks 23 weeks 19 weeks O 16 weeks