Question: Given the following activity network: Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10

Given the following activity network: Activity A1
Given the following activity network: Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10 weeks with a 50% probability. What is the project completion time under the best-case scenario, that is, A3 is early and takes 4 weeks? Multiple Choice 9 10