Question: Given the following activity network: Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the slack of A3

Given the following activity network: Activity A1
Given the following activity network: Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the slack of A3 ? Multiple Choice 8 weeks 4 weeks 0 weeks 6 weeks