Question: Given the following activity network: Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10
Given the following activity network: Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10 weeks with a 50% probability, What is the project completion time under the best-case scenario, that is, A3 takes 4 weeks