Question: Given the following activity network: Az A 1 A 2 A , AA A . Activity A 1 takes 3 weeks. A 2 takes 8

Given the following activity network: Az A1 A2 A, AA A. Activity A1 takes 3 weeks. A2 takes 8 weeks, A3 takes 10 weeks A4 takes 9 weeks. AS takes 2 weeks, A6 takes 4 weeks, AZ takes 4 weeks. What is the critical path of the project? 1,2,3, A5, A7 O A1, A2, A3, A4, A5, A6, A7 O A1, A2, A3, A6, A7 A1, A2, A4, A6, AZ