Question: Given the following activity network: Three nodes - A 1 , A 2 , A 3 ; two paths - A 1 , A 2

Given the following activity network: Three nodes - A1, A2, A3; two paths - A1, A2 and A1, A3.
Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10 weeks with a 50% probability. What is the project completion time under the worst-case scenario, that is, A3 is late and takes 10 weeks?
Question 7 options:
A)
10
B)
15
C)
9
D)
12