Given the following activity network: Three nodes - A1, A2, A3; two paths - A1, A2 and A1, A3.
Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the latest completion time of A3?
A.7
B.15
C.10
D.13