Question: Given the following activity, Optimistic, Most likely and Pessimistic time : Calculate the Estimated time for each activity Draw the Activity on Arrow network diagram.
Given the following activity, Optimistic, Most likely and Pessimistic time :
Calculate the Estimated time for each activity
Draw the Activity on Arrow network diagram.
Calculate the estimated Time TE
Determine the total, safety and independent slacks for activities and
Determine the critical path
What is the probability of completing the project in days?
What day does the project have a probability of completion?
tableActivityPredecessor,Optimistic time daysMost likely time daysPessimistic time daysABCADAEBFCGD E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
