Question: Given the following activity, Optimistic, Most likely and Pessimistic time : Calculate the Estimated time for each activity Draw the Activity on Arrow network diagram.

Given the following activity, Optimistic, Most likely and Pessimistic time :
Calculate the Estimated time for each activity
Draw the Activity on Arrow network diagram.
Calculate the estimated Time (TE)
Determine the total, safety and independent slacks for activities 1-3 and 2-5
Determine the critical path
What is the probability of completing the project in 18 days?
What day does the project have a probability of 95% completion?
\table[[Activity,Predecessor,Optimistic time (days),Most likely time (days),Pessimistic time (days)],[A,-,5,11,11],[B,-,1,7,13],[C,A,2,5,8],[D,A,4,7,10],[E,B,8,11,14],[F,C,1,4,7],[G,D, E,0,6,6]]
 Given the following activity, Optimistic, Most likely and Pessimistic time :

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!