Question: Given the following activity, Optimistic, Most likely and Pessimistic time: 1. Calculate the Estimated time (TE) for each activity. Activity Optimistic time (days) Pessimistic Time

Given the following activity, Optimistic, Most
Given the following activity, Optimistic, Most likely and Pessimistic time: 1. Calculate the Estimated time (TE) for each activity. Activity Optimistic time (days) Pessimistic Time (days) Estimated Time Most Likely Time (days) 11 7 13 1-2 1-3 2-4 2-5 3-5 4-6 8 11 4 7 5-6 Activity 1-2 means activity between events 1 and 2. TE =Estimated Time