Question: Given the following additional duration data for this project: Activity Best Case Most Likely Worst Case H 4 5 7 I 3 6 7 J

Given the following additional duration data for this project:
Activity Best Case Most Likely Worst Case
H 457
I 367
J 345
K 223
L 568
M 235
N 7910
O 122
P 446
Q 235
5) What is the expected duration of activity P?(enter 2 decimal places)
6) What is the standard deviation of activity N?(enter 2 decimal places - if it is less than one, enter the zero and the decimal point)
7) What is the standard deviation of the project? (enter 2 decimal places - if it is less than one, enter the zero and the decimal point)
8) Assuming the expected duration of the project is 25.5 and given the following z table, what is the probability the project will be finished by the original most likely time? (enter it as a decimal - with 2 decimal places - enter the zero and the decimal point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!