Question: Given the following PERT data for a given project: Activity Duration time, weeks Immediate predecessors Optimistic (o) Most Likely (m) Pessimistic (p) A 1 2
Given the following PERT data for a given project:
| Activity | Duration time, weeks | Immediate predecessors |
|
| ||
| Optimistic (o) | Most Likely (m) | Pessimistic (p) | ||||
| A | 1 | 2 | 3 |
|
| |
| B | 2 | 3 | 4 |
|
| |
| C | 4 | 5 | 6 | A |
|
|
| D | 8 | 9 | 10 | B |
|
|
| E | 2 | 5 | 8 | C, D |
|
|
| F | 4 | 5 | 6 | B |
|
|
| G | 1 | 2 | 3 | E |
|
|
- Calculate the average duration time and the standard deviation per activity? (4 pts)
- Find the critical path(s) for this project? (4 pts)