Question: Given the following PERT data for a given project: Activity Duration time, weeks Immediate predecessors Optimistic (o) Most Likely (m) Pessimistic (p) A 1 2

Given the following PERT data for a given project:

Activity

Duration time, weeks

Immediate predecessors

Optimistic (o)

Most Likely

(m)

Pessimistic (p)

A

1

2

3

B

2

3

4

C

4

5

6

A

D

8

9

10

B

E

2

5

8

C, D

F

4

5

6

B

G

1

2

3

E

  1. Calculate the average duration time and the standard deviation per activity? (4 pts)
  2. Find the critical path(s) for this project? (4 pts)