Question: Given the following data, by how much will safety stock increase (decrease) if Supplier A is replaced by Supplier B? Supplier A Lead Time 25
Given the following data, by how much will safety stock increase (decrease) if Supplier A is replaced by Supplier B?
| Supplier A Lead Time | 25 days |
| Supplier B Lead Time | 16 days |
| Average Daily Customer Demand | 100 units per day |
| Standard Deviation of Daily Customer Demand | 15 units |
| Mean Absolute Deviation (MAD) | 25 |
| Desired Service Level | 97% |
| Z Score for Desired Service Level | 1.88 |