Question: Given the following data, calculate EAC based on Cumulative Cost performance Index as the performance factor. Round to the nearest dollar. BAC=1000; BCWS =500;
Given the following data, calculate EAC based on Cumulative Cost performance Index as the performance factor. Round to the nearest dollar. BAC=1000; BCWS =500; BCWP= 325, ACWP=500