Given the following activities required for staging a community play on Independence Day,
(a) Construct an AON diagram.
(b) Determine the earliest completion time for the play and the critical path.
(c) Based on the critical path, what completion date are you 80% confident of achieving? 40% confident?
(d) Will a 1-day delay in this project beserious?