Question: Given the following data, develop MRP plans for items C, D, E and F. MPS start for end items: The following table shows the MPS
Given the following data, develop MRP plans for items C, D, E and F.
MPS start for end items: The following table shows the MPS start information for two end items: item A and B. For example, we have a plan to start producing 70 units of end item A in week 2.
| End item | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 |
| A | 30 | 70 | 80 | |||
| B | 60 | 110 |
Bill of materials:
- End item A is made of 1 unit of item C and 1 unit of item D.
- Item D is made of 2 units of item E and 2 units of item F.
- End item B is made of 1 unit of item C and 2 units of item F.
MRP-related information for each item:
| Item | Leadtime (weeks) | Lot sizing | Safety stock requirement | Available on-hand inventory | Scheduled receipts |
| C | 2 | L4L | 0 | 60 | 80 in week 1 |
| D | 1 | L4L | 0 | 80 | None |
| E | 1 | FOQ (200) | 0 | 90 | None |
| F | 1 | FOQ (100) | 10 | 30 | 200 in week 1 |