Question: Given the following data, develop MRP plans for items C, D, E and F.MPS start for end items: The following table shows the MPS start
Given the following data, develop MRP plans for items C, D, E and F.MPS start for end items: The following table shows the MPS start information for two end items: item A and B. For example, we have a plan to start producing 70 units of end item A in week 2.
| END ITEM | WEEK 1 | WEEK 2 | WEEK 3 | WEEK 4 | WEEK 5 | WEEK 6 |
| a | 30 | 70 | 80 | |||
| b | 60 | 110 |
Bill of materials:- End item A is made of 1 unit of item C and 1 unit of item D.- Item D is made of 2 units of item E and 2 units of item F.- End item B is made of 1 unit of item C and 2 units of item F.MRP-related information for each item:
| ITEM | LEAD TIME (WEEKS) | LOT SIZING | SAFETY STOCK REQUIREMENT | AVAIL ON HAND INVENTORY | SCHEDULED RECEPTS | ||
| C | 2 | L4L | 0 | 60 | 80 in week 1 | ||
| D | 1 |
| 0 | 80 | NONE | ||
| E | 1 | FOQ (50) | 0 | 60 | NONE | ||
| F | 1 | FOQ (100) | 10 | 30 | 200 in week 1 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts