Question: Given the following data, develop MRP plans for items C, D, E and F.MPS start for end items: The following table shows the MPS start

Given the following data, develop MRP plans for items C, D, E and F.MPS start for end items: The following table shows the MPS start information for two end items: item A and B. For example, we have a plan to start producing 70 units of end item A in week 2.

END ITEM WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6
a 30 70 80
b 60 110

Bill of materials:- End item A is made of 1 unit of item C and 1 unit of item D.- Item D is made of 2 units of item E and 2 units of item F.- End item B is made of 1 unit of item C and 2 units of item F.MRP-related information for each item:

ITEM LEAD TIME (WEEKS) LOT SIZING SAFETY STOCK REQUIREMENT AVAIL ON HAND INVENTORY SCHEDULED RECEPTS
C 2 L4L 0 60 80 in week 1
D 1
L4L
0 80 NONE
E 1 FOQ (50) 0 60 NONE
F 1 FOQ (100) 10 30 200 in week 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!